Elon Musk's The Boring Company and the Metro Nashville Airport Authority signed a 40 year license agreement on November 18, 2026, for a Music City Loop station at Nashville International Airport. The Nashville Business Journal and The Tennessean reported the signing that day, and the company announced it the next day, as covered by WSMV and FOX 17.
Clients ask me about transportation projects like this because they are part of how people think about getting around Nashville. In this article I walk through what was signed, where the station would go, who pays and on what terms, the published route from downtown to the airport, how far the tunneling has gone, and what the timeline looks like. I have tried to stick to what the public record supports and to be clear about what is still unknown.
The short version
- The license was signed on November 18, 2026, for a term of 40 years.
- The planned station would be about 22 feet from the terminal entrance, according to the company and airport CEO Doug Kreulen.
- Under terms the airport board approved on February 18, 2026, the company pays to design, build, operate and maintain the station, with no airport capital.
- Those terms include a $300,000 annual license fee that rises 3 percent a year, $5 for each airport pickup and each drop off, and a $600,000 reimbursement of airport expenses.
- No opening date has been set for the airport station.

What was signed
On November 18, the airport authority and The Boring Company signed a long term agreement giving the company the ability and space to operate its service at BNA, as the Nashville Business Journal reported. The term is 40 years. That length appears in the terms the airport board approved in February, in reporting by WSMV and Aviation Pros, and in the company's own announcement.
The February terms also allowed two 5 year extensions. That is how you get to a possible total of 50 years, which matters when we look at the projected revenue below.
One caution up front. LOOP Nashville, which covered the signing, notes that the executed November 18 contract has not been independently reviewed and that some terms could have changed from what the board approved in February. When I wrote this, I could not find a press release about the signing from the airport authority on its own website. So when I describe fees and other details below, I am describing the terms approved in February, not a line by line reading of the signed document.

Where the station would go
The company says the planned station would be 22 feet from the terminal entrance. Airport CEO Doug Kreulen made that comparison at an October board meeting, before the signing, as reported by The Tennessean on October 28 and by LOOP Nashville. He said that compares with about a 600 foot walk for passengers using Uber and Lyft.
According to plans reported by The Tennessean, the station would sit in the current taxi and limousine pickup area. In that reported concept, vehicles would come out of the tunnels near Airport Service Road and continue a short way above ground to the station. That is a concept described in news coverage, not a surveyed path of the finished work.
Kreulen also said taxi and limousine operations may move to the northern side of the terminal, and that those arrangements were still being developed. I mention that only as background. It has not been announced as a finished relocation.
You may also see an older line in the company's FAQ saying the airport alignment ends within 100 feet of the airport. More recent reporting and the company's announcement put the passenger station about 22 feet from the terminal entrance, so that is the figure I use here.

Who pays, and the fee terms
Under the terms the airport board approved on February 18, 2026, The Boring Company covers the design, construction, operations and maintenance of the station, with no airport capital. The company restated that when it announced the signing, according to WSMV and Aviation Pros.
The February terms set three main payments to the airport:
- A $300,000 annual license fee that rises 3 percent a year.
- $5 for each airport pickup and each drop off, subject to adjustment.
- A $600,000 reimbursement of airport expenses.
The board materials go into more detail. They describe the $300,000 license fee as a $150,000 fixed portion that starts with above ground construction, plus a $150,000 performance portion paid through a $0.25 per ride fee, with catch up provisions. They also break the $600,000 reimbursement into staged payments.
About these numbers: the fee figures come from the terms the airport board approved on February 18, 2026. The agreement signed on November 18 could differ. Aviation Pros presents them as terms of the signed agreement, but LOOP Nashville says that has not been independently confirmed from the executed document.

The $343 million figure is a projection
Some headlines have described this as a $34 million deal. That number is the airport's February projection for license fees only, over a possible 50 year term. The same airport documents project about $309 million in pickup and drop off fees over that period. Together that comes to about $343 million. WSMV reported that the company also cited about $343 million over a potential 50 year term, including extensions. The Nashville Banner covered these revenue projections when the board acted in February.
About the $343 million: it is a projection over a possible 50 years, not a guaranteed payment. It assumes the 40 year term is extended to 50 years. Actual revenue would depend on ridership, the fees in effect, and whether the term is extended at all.

The downtown to BNA corridor
The company's Music City Loop page publishes the airport alignment as a list of streets. It starts near the State Capitol, at Lot 16, runs south along Rosa L. Parks Boulevard to 8th Avenue South, then follows Lafayette Street and Murfreesboro Pike to Donelson Pike, and ends at the airport.
The map below draws those named streets from OpenStreetMap data. It shows a corridor, not a surveyed tunnel path. The tunnels are underground, and the published street list tells you the general route. It does not tell you the exact position of a tunnel under any particular block or property.
The same FAQ also describes a second alignment along Broadway and West End. This article is about the airport station agreement, so I have not mapped that line.

How far the tunneling has gone
Two machines are already tunneling under downtown. As of October 31, state records put the two machines at about 1.13 miles combined, according to City Cast Nashville, citing reporting by The Tennessean.
WKRN, citing company documents, reported on November 20 that one tunnel was about 3,700 feet and the other about 2,300 feet. That adds up to about 6,000 feet, which matches the 1.13 mile figure.
I have not included any estimate of when crews might reach the airport. Some coverage has done its own math based on the pace so far, but that is not an official schedule, and I do not want to present it as one.
Timeline: what we know and what we do not
- February 18, 2026: the airport board approved the terms, including the 40 year term, two 5 year extensions, and the fee structure described above. (board presentation)
- October 1, 2026: the company's update said station design and permitting at the airport were still underway. (FOX 17, LOOP Nashville)
- October 28, 2026: The Tennessean reported the station plans, including the 22 foot distance and the location in the taxi and limousine pickup area. (The Tennessean, LOOP Nashville)
- October 31, 2026: state records put the two downtown machines at about 1.13 miles combined. (City Cast Nashville)
- November 18, 2026: the airport authority and The Boring Company signed the 40 year license. (Nashville Business Journal, The Tennessean)
- November 19, 2026: the company announced the agreement. (WSMV, FOX 17, Aviation Pros)
About the opening date: there is no opening date. This agreement does not set an opening date for the airport station. The company has targeted early 2027 for initial passenger service on the Music City Loop. That is the company's target, not a confirmed opening for the airport station. FOX 17 reported that no opening date has been announced for the airport station.

What it could mean if you are buying or selling near the corridor
I get asked whether projects like this change home values. The honest answer is that I cannot tell you, and I would be careful with anyone who says they can. There is no opening date for the airport station, the public documents do not show a surveyed tunnel path, and the signed terms have not been published in full.
What I can do is help you keep the facts straight for a specific property:
- Look at where a home sits relative to the published street corridor, keeping in mind that the corridor is not a tunnel path.
- Follow public records and board actions from the airport authority and Metro Nashville as they come out, rather than relying on headlines.
- Ask about any construction, permits, or street work near a property so you can plan around showings, inspections, and timing.
- Price a home using recent sales and current competition, the same way I would anywhere else in Nashville.
If you are selling, I would not market a home based on a transit service that does not have an opening date. If you are buying, I would treat the Loop as one piece of information among many, not a reason to rush or to wait.

Sources
- Nashville Business Journal, November 18, 2026: Airport, Boring Co. finalize agreement for ride share tunnels under BNA
- The Tennessean, November 18, 2026: coverage of the signed agreement
- The Tennessean, October 28, 2026: station plans at the airport
- LOOP Nashville, November 18, 2026: The Boring Company signs Nashville airport agreement
- LOOP Nashville, October 29, 2026: Music City Loop BNA station near the terminal entrance
- WSMV, November 20, 2026: The Boring Company announces 40 year agreement for a Music City Loop station
- FOX 17, November 19, 2026: The Boring Company signs deal for a Music City Loop station at the Nashville airport
- Aviation Pros, November 19, 2026: Nashville International Airport finalizes tunnel agreement with The Boring Company
- Metro Nashville Airport Authority board presentation, February 18, 2026 (PDF)
- Nashville Banner, February 19, 2026: the February letter of intent and revenue projections
- The Boring Company: Music City Loop project page and FAQ, including the published alignment
- City Cast Nashville, November 19, 2026: tunneling progress as of October 31
- WKRN, November 20, 2026: Music City Loop tunnels stretching thousands of feet under Nashville
- OpenStreetMap contributors: map data, Open Database License
The Nashville Business Journal and The Tennessean articles are behind a paywall. Where I relied on them, I used the public headline and lede or the details as reported by LOOP Nashville and City Cast Nashville.
If you have questions about the Music City Loop or about buying or selling a home in Nashville, please reach out. I would be glad to talk it through with you.